You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project, and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?

Respuesta :

Answer:

C. Matrix Structure

Explanation:

Based on the information provided within the question it can be said that the project management structure that is being used is called a Matrix Structure. This is an organizational structure in which a company sets up it's relationship between the different departments as a grid or matrix as opposed to a normal hierarchy. Where each group is in charge of their own thing but can interact with anyone on the grid.