The flowtime of the last job in a single work center’s schedule is 7 days. What is the makespan of this schedule?

Respuesta :

Answer:

7 days

Explanation:

Makes-pan means the time it takes to complete a schedule. Last job took 7 days to complete and it was a single job, which means its makes-pan was 7 days as well.