7070
To complete a task in 16 days a company needs
5 people each working for 6 hours per day.
The company decides to have
8 people each working for 4 hours per day.
Assuming that each person works at the same rate,
how many days will the task take to complete?
o

Respuesta :

Answer:

do you want the answer because i am telling your teacher that you are cheating

Step-by-step explanation: